2020-2021 Upgrade /renewal of FD30 front entrance doors at 3 storey blocks

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Authority to go to market and procure a contract. Seek delegated authority to award the contract following the outcome of the tendering process.

Decisions:

RESOLVED:  That

 

(1)          officers be authorised to undertake a procurement process for a contractor to deliver a variety of FD30 fire doors across the Borough, as part of general improvements to the safety of Harrow Council’s housing stock, funded entirely from HRA capital resources with no impact on General Fund in financial year 2020-21;

 

(2)          the Corporate Director, Community, following consultation with the Portfolio Holder for Housing, be authorised together with the Director of Finance to enter into the procurement and implementation of the contract to the value specified within the capital programme.

 

Reason for Decision:  Due to the estimated value of the project exceeding the key decision schedule Cabinet authorisation was required to comply with the Council’s Contract Procedure Rules.

 

Alternative Options Considered and Rejected:  As set out in the report.

 

Conflict of Interest relating to the matter declared by Cabinet Member/Dispensation Granted:  None.

Report author: Nick Powell

Publication date: 10/01/2020

Date of decision: 09/01/2020

Decided at meeting: 09/01/2020 - Cabinet

Effective from: 18/01/2020